New changing rooms in Rockfield Park

Meeting of DĂșn Laoghaire Area Committee

Written:

23rd February 2009

Question: Councillor M Baker

To ask the Manager for an update on when the new changing rooms will be commenced and completed in Rockfield Park (formerly Newtownpark Lands Park)?

Reply:

Seven contractors have been selected from an expression of interest process and tender documents will be forwarded to them for their consideration and formal tender submissions within the next two weeks. We would anticipate receipt of tenders mid April with the awarding of the successful contract in May 09. Depending on the construction programme of companies it is expected that works would commence shortly after.