Blackrock Library Update
Written: 11 years ago
The temporary library premises will close at the end of January 2014 to allow us to transfer staff, stock and equipment to the new facility. We have also agreed a programme of dilapidations with the landlord and these works must be completed during February.
The library staff will transfer over to the new facility to prepare it for public opening. The Architects have told us that works could be completed by end of January though we are allowing slippage to end of February. The library space has increased from 454m2 to 537m2.
The new library should open during April 2014.”
I am delighted that the building works are finally reaching a conclusion and that users of the Blackrock Library can look forward to a bigger and better library experience in 2014.